UNINTERRUPTED FLOW URBAN GREENING ENVIRONMENTALLY FRIENDLY HARBOUR PROTECTION SPACIOUS VIBRANCY CONNECTION

Works Progress

North Point

Construction Activities

Works in North Point District are undertaken by two contracts: a) Tunnel (North Point Section) and Island Eastern Corridor Link Contract (Contract No: HY/2009/19) and b) Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning Contract (Contract No: HY/2011/08) 


a) Tunnel (North Point Section) and Island Eastern Corridor Link (Contract No: HY/2009/19) 
This contract includes the construction of a 300-metre-long tunnel section, together with an approach road and modification of a section of Island Eastern Corridor (IEC). Associated works such as landscaped deck, noise barriers, noise semi-enclosures, road drainage and landscaping works are also included in this contract.

b) Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning (Contract No: HY/2011/08) 
This contract is for the construction of the Tunnel Buildings in North Point District, i.e. East Ventilation Building (EVB), East Vent Shaft (EVS), Administration Building (ADB), construction of tunnel cladding works, installation of route-wide tunnel electrical and mechanical works as well as the traffic control and surveillance system. The contract scope also includes testing and commissioning works.

Main Temporary Traffic Arrangements

To facilitate the construction works in North Point, Temporary Traffic Arrangements will be/have been implemented as follows:

 

a) Road resurfacing works at Hing Fat Street will be carried out in stages during day time of the public holidays and Sundays in April 2021. For more details, please refer to below poster .

 

b) To facilitate the works of Central – Wan Chai Bypass, new temporary traffic arrangements have been implemented at Island Eastern Corridor Eastbound (North Point Section) bridge deck near CWB North Point Tunnel Portal from 27 March 2021. For more details, please refer to below poster .

 

c) Retrofitting of a pedestrian crossing at Wing Hing Street (near Hing Fat Street) and realignment of kerb line at Wing Hing Street were completed. The new pedestrian crossing was opened for use on 8 January 2021, while the existing crossing at Hing Fat Street was then closed. The outstanding works at Hing Fat Street will be completed in the first quarter of 2021. For more details, please refer to below leaflet.

 

d) Further to a trial run conducted during 5 to 23 September 2019 on the section of Island Eastern Corridor (IEC) westbound between Henrietta Secondary School and Harbour Heights, temporary traffic arrangements on IEC westbound has been implemented from 23 October 2019 to facilitate road works and the installation of remaining noise enclosures. For more details, please refer to below poster .

 

UNINTERRUPTED FLOW URBAN GREENING ENVIRONMENTALLY FRIENDLY HARBOUR PROTECTION SPACIOUS VIBRANCY CONNECTION

Share |

You can subscribe to CWB eNews.


CAPTCHA Image Reload Image

   
Graphics represent an artist’s impression of the works